Contractor:
Draper Construction & Commercial Roofing of Oklahoma City, OK
Project Location:
X-Clusive Cannabis in Oklahoma City, OK
Construction Date:
May 2025
Products Used:
- Eversol Foam
- Evercoat HT (two colors)
- Eco Level
- Everseal
Project Description:
This building’s previous SPF roof system has failed. The roof leaked constantly and the owner decided to put a tarp on it until they could find a roofer with SPF experience. Given the high volume of foot traffic from customers entering and exiting throughout the day, addressing the leaks promptly was essential to ensure safety and maintain a professional environment.
Project Steps:
- Scarify the roof to prepare for new foam and coating
- Bag and dispose of old foam
- Tear off additional areas (wet) and fill back
- Install foam stop, 24 gauge, 4 inch drip edge of perimeter
- Install black foam primer where needed to prepare roof surfaces
- Cut blisters and other damaged foam from the roof
- Install 1 ¼" - 1 ½" of sprayed-in-place polyurethane foam across the entire roof surface flashing around any other roof penetrations
- Additional foam for drainage
- Apply medium gray base coat, at approx. rate of 1.5 gal/sq, back-rolling to fill any pin holes
- Apply white top coat, at approx. rate of 1.5 gal/sq